Sunset Drive Office Building
11811 S. Sunset Drive
Olathe, KS 6606

PBC Project Authorization $30,050,000
Delivery Method Design-Build
Status

Construction is substantially complete

Design-Build Team: McCownGordon/360 Architects
Projected Occupancy Date February 2006
Anticipated future PBC action None

The Sunset Drive Building is complete and operational. Card access work is underway and is anticipated to be completed within the next two weeks. Audio-visual equipment will be installed over the next six weeks. All Departments have moved into the building with the exception of the Water Quality Lab and County Appraiser .

Read more about the project and the building in the official press release.

View a slide show of the construction of the building

  Projected Department Move In Dates:

Facilities February 27
Water Quality Lab TBD
Wastewater March 3
MedAct March 31
Extension March 31
HS&A April 7
Environmental April 7
Appraiser June 23

 


Olsthe, KS