JCDS – Elmore Center Renovation
| PBC Project Authorization | $4,481,500 |
| Delivery Method | Construction Management at Risk |
| Status | Schematic Design |
| Architect | GLPM/Treanor Architects (Term & Supply) |
| Construction Manager | Not Yet Selected |
| Projected Completion Date | First Quarter, 2009 |
| Anticipated Future PBC Action | Award of construction contract |
Space programming and preliminary design is proceeding with Term & Supply architect. Parking lot and outdoor activity area preliminary design is complete.
Schematic building massing as presented at Neighborhood Meeting 5/17/06