County Communications Center

 

PBC Project Authorization $20,975,000
Delivery Method Design/build with full bridging design
Status Under Construction.
Bridging Architect HTK Architects
Desig/ Build Team McCownGordon Construction & PGAV Architects
Projected Occupancy Date

Occupancy Q1 2009; Operational Q2 2009

Anticipated Future PBC Action

Award of various equipment and furnishing contracts.

Precast and steel erection are nearly complete and the vegetated roof is underway. Most major mechanical, electrical and plumbing (MEP) systems are in place with construction continuing until an anticipated substantial completion date in the fourth quarter of 2008. Specialized emergency communications equipment will be installed and tested into the first quarter of 2009.

Schematic building massing as presented at Neighborhood Meeting 5/17/06

VIew our exclusinve construction site web camera.